23.04.2026

RF MAH Sp. z o.o.

Growth is an integral part of our business


Investment in new technologies is a key element in the company's development. We have begun preparations for the installation of an advanced boring machine, which we plan to launch in early August.


✅The old flooring has been removed from the machine's installation site.

✅A special foundation design has been completed.

✅Precision in the foundation design and construction is maintained. Permissible foundation deformation is just 0.01 mm per meter.

✅Approximately 50 m³ of concrete, weighing 125 tons, has been poured into the foundation!

✅We have used 4 tons of reinforcing steel.


The development of RF MAH involves concrete steps, and we will share the details of this investment once installation begins in May.